Hi Experts,

My requirement is like this,

I am making a sub-contracting PO of material 'A' for 600 numbers.

For this i need component 'B' 1800 numbers.

For sending 1800 numbers of B to sub-contractor, i have to select 6 batches of 300 numbers.

When i create sub-contracting PO, in the BOM components view, i am not able to do the Batch determination to select the multiple batches.

Please guide me to solve this issue.