ECC not using TKOMK-FBUDA from RV60AFZZ

Hi all,

We just upgraded from 46C to ECC 6.0 in RV60AFZZ we had a statement to move the billing date to the services rendered date

FORM USEREXIT_PRICING_PREPARE_TKOMK.

MOVE TKOMK-FKDAT TO TKOMK-FBUDA.

We can see the breakp point being hit and set but the service render date is not being used in pricing.

We set up rebate agreements monthly, and is a billing needs cancelled and rebilled to correct an error the rebill is picking up the prior months date, instead of the billing date in the current month. This worked fine in R/3 46C for many years.

In ECC the only work around I have is to go into each line item and do a new pricing before saving the document.