SNP is not picking transportation lane

Former Member
0 Kudos

A valid transportation lane exists for a material that is sourced by DC B from Plant A.

A valid transporation lanes exists between these two however SNP Run does not pick the transporation lane and a Pur Req is created without a source iniside it.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Foun dit. The Aggregate Planning Check Box was not checked in the means of transport in the transportation lane.

Former Member
0 Kudos

please check if the Preq is cerated by heuristics or manually created..if it is created by heuirstics then go to RRP3 double click on the Receipt and in the Activities if you see Transportation click on it and check the 'current length days' and check if it is matching with Transportation duration in the Tlane...you can also try rerunnng the heuristics and check if you have same issue

Former Member
0 Kudos

Make sure you have Product maintained for both source and target location.

/SAPAPO/MAT1

Also check if any Blocking Indicator for Source of Supply is set in TL(/SAPAPO/SCC_TL1 - Master Data -> Transportation Lane -> Transportation Lane )

Manish