Configuration in T399D table - What is IMG path?

Former Member
0 Kudos

People,

do you know what is the configuration path in IMG, for the information in t399d table?

Thanks a lot!

Accepted Solutions (1)

Accepted Solutions (1)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Use Transactions;

OPPQ - Plant Parameters for MRP

OPPR - MRP Parameters for MRP Group

Paths are;

SPRO > Production > Material Requirements Planning > Plant Parameters > Carry Out Overall Maintenance of Plant Parameters

SPRO > Production > Material Requirements Planning > MRP Groups > Carry Out Overall Maintenance of MRP Groups

Answers (2)

Answers (2)

former_member581212
Active Contributor
0 Kudos

hi,

SPRO --> Production --> Material Requirements Planning ---> Plant Parameters ---> Carry Out Overall Maintenance of Plant Parameters

SPRO--- > Production -> Material Requirements Planning -


> MRP Groups--- > Carry Out Overall Maintenance of MRP Groups

Hope it helps....

Regards

Priyanka.P

Former Member
0 Kudos

Thanks a looooooooot!

former_member192897
Active Contributor
0 Kudos

Table T399D is for Control Parameters for MRP

The Following Transactions will Update the Transparent Table T399D

OPPQ MRP Parameters for MRP

OPPR Parameters for MRP Group