Dear All,

I have done settlement of project expenses for the amount of Rs.600 which consists of Rs.100Rs.200Rs.300) three times settlement , and after settlement when I do the reversal using processing type u201CFullu201D using the transaction type : CJ88, the system has to take all the settlement which I have done for Rs.600, but it is taking for reversal of Rs.300 only that it is last settlement , not Rs.600, why the system is not taking full reversal of all settled amount. Any one come across this case, please provide the solution.

Regards,

S.Suresh