Caliberation Cycle

Can anybody guide me the full Caliberation cycle of equipment in detail in QM

Regards,

A

Former Member
Former Member replied

hi

IE01:Equipment

IP11: Maintainence Strategy

IA05: Task List

IP42: Maintainence Plan

IP10: Scheduling Of plan

IP30: Job Planning

Create Measuring inspection characteristics....QS21

Create Task list by assiging ispection point as 300 /310...IA05

Assign MIC & Strategy to the task list....IA05

Create PM order for calibration order which should have ...IW31 (inspection type assigned as 14 as std)

Assign Task list to PM Order...IW32

Release PM order....IW32

You will get inspection lot

Provide readings against the inspection lot...QE17/QE51

Provide Usage decieon for the FL/ EQ...QA11

If you aregoing for Maint plan then crete maint item...IP41

Assign this to maint plan & scheduling paramertes

Schedule maint plan...IP10/IP30

Get PM Orders Release it Get Inspection lots..IW38

-ashok