Budget Supplement and Planning Supplement

Hi All,

Is there any planning supplement in PS or Investment management?

As far as i know there is a tcode for budget supplement. But how can i put supplement in planning?

Plz advice.

Cheers,

Nies

Former Member
Former Member replied

In OK02 create a status profile for WBS element and in that create a status for example "COPL" and allow the "Write Plan Line Item" business transcation.

Attach this status profile to all the WBS element.

Let me know if u need futher clarification.

Venkat