on 10-10-2008 9:54 AM
Hi All,
Material no gets skips if you do not save and exit MM01 transaction and go for creating next time. Is there any solution for the same?
Rrgards,
Rakesh
Hello
This is because of the buffering of material number object. Even if you dont save the material, it will be skipped as a number will be taken to buffer.
To avoid this, go to SNRO
Give the object MATERIALNR
And remove the tick for main memory buffering and save.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This is a standard behavior, if you do not want that particular internal number to be skipped, you will need to re-set the number range (the current No.)
Regards
Merwyn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.