on 10-10-2008 9:06 AM
hi,
has anyone come across this SAP problem?
I use BAPI_NETWORK_COMP_ADD to add a material to a Network.
It adds fine, and shows up in CJ20N.
However, if you go to the Plan/Actual Cost (CN41), there is no cost associated.
Okay. I used BAPI_NETWORK_COMP_CHANGE and it finally added the Cost to the Material Component.
HOWEVER, it doesn't have the Cost on Network/WBS element level.
Therefore, the plan/actual Cost for Project Definition is wrong.
Can anyone help?
If you add a material component manually in CJ20N and then change quantity, it works fine.
The thing is, CJ20N uses so many memory objects, it's hard to copy what it does.
Thank you
Bill
it was caused by me.
I first delete Network Comp,
commit,
then add new Network Comp,
Commit,
this somewhere screw up the calculations.
Therefore, i must do,
delete network comp
add new comp
Commit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
after the transfer,
go to CJ20N and check the network control parameter, where the cost calculation parametrs are maintained.
1- cost to be calculated
2- cost to be calculated aftr release
3-donn plan cost
select the correct one
again check the costing variant and check the material valuation
rgds
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.