Material Component to Network - BAPI_NETWORK_COMP_ADD

Former Member
0 Kudos

hi,

has anyone come across this SAP problem?

I use BAPI_NETWORK_COMP_ADD to add a material to a Network.

It adds fine, and shows up in CJ20N.

However, if you go to the Plan/Actual Cost (CN41), there is no cost associated.

Okay. I used BAPI_NETWORK_COMP_CHANGE and it finally added the Cost to the Material Component.

HOWEVER, it doesn't have the Cost on Network/WBS element level.

Therefore, the plan/actual Cost for Project Definition is wrong.

Can anyone help?

If you add a material component manually in CJ20N and then change quantity, it works fine.

The thing is, CJ20N uses so many memory objects, it's hard to copy what it does.

Thank you

Bill

former_member868917
Discoverer
0 Kudos

HI

I have used the BAPI_NETWORK_COMP_ADD to create material component to activity but i have faced some issue regarding return then i need mention method ,object type ,internal object id and external object id

can you help me on this or can you give your number.

8074703782

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

it was caused by me.

I first delete Network Comp,

commit,

then add new Network Comp,

Commit,

this somewhere screw up the calculations.

Therefore, i must do,

delete network comp

add new comp

Commit

Former Member
0 Kudos

Hi,

after the transfer,

go to CJ20N and check the network control parameter, where the cost calculation parametrs are maintained.

1- cost to be calculated

2- cost to be calculated aftr release

3-donn plan cost

select the correct one

again check the costing variant and check the material valuation

rgds

ashis