cancel
Showing results for 
Search instead for 
Did you mean: 

Pricing procedure for scheduling agreement

Former Member
0 Kudos

All SAP Gurus,

We are preparing the scheduling agreement.

We want to know which Pricing procedure is attached.

How it can be known while creating schudiling agrmment or displaying scheduling agreement (as user will not be having access to other transactions)?

Regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

not answered.

srinivasa_maruvada
Active Contributor
0 Kudos

Hi

Pricing procedure is not based on Scheduling Agreement or PO. It is based on material. check at spro-Materials Management-Purchasing-Conditions-Define Price Determination Process-Define Calculation Schema.

Cheers

Srinivas

Former Member
0 Kudos

Hi,

I know that, what I'm trying to know us 'can we know which pricing procedure is attached scheduling agreement'

(We can see the pricing procedure attached to PO from condition tab).

Regards,