on 10-10-2008 8:09 AM
How does the control key come into the plant maint. order task list as default?
Hi
The control key is copied from the work centre default values screen.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It get copied from the Default Values screen of the Work Center.
As soon as you assigns the Work center to the Operation, it copies the Control key.
Regards,
Shyamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
if you maintain teh control key in the work centre in defult values tab,
then it will come in the task list.
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.