Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Material problems and PO not created

Hello,

SRM Classic Scenario.

We tried to create shopping cart with a material in ECC and in SRM (can be viewed in COMM_PRODUCT)

SC is in Approved status but "Contains Errors" as well. Checked the Backend Application Error > Alert Display in RZ20 (SRM side)

Shopping cart 0010000387 (PReq. 0090000012): ME 060 No procurement defined for material 100-ABB 9015C

For any other material only PR is created. Material number is not passed on to PR from catalog and PO is not created. Checked number ranges (SRM and ECC), back end document types, system type.

Pls advise.

Thanks

Helpful Answer

by