Production Order Header Status

Hi

I am having a production order with 4 operations. when i am confirming the first operation as partial confirmation because i am just confirming only partial quantity, the whole production order status is set to PCNF. Even though i am finally confirming the same operation finally and confirming all the other operations also finally, the order status is not changing to CNF. it is still in the PCNF . how do i get it to CNF status? because the PCNF status for the order will create other problems.

The operation statuses for the same order give correct statuses as PCNF or CNF or milestone. The problem is only with order header status.

Can someone please solve this issue. Points assured

Regards

Chandra

Former Member
Former Member replied

Hi,

In tcode OPK4 - Define confirmation parameter select your plant & order type.

In 2nd tab page, select Confirmation type - Automatic final confirmation.

So when doing opn confirmation if the qty is equal or more than order qty, system automatically set to Final confirmation.

If the confirmation qty is less than order qty, system automatically set to partial confirmation.

Regards,

Dharma