I purchased one asset and i posted that one is a AUC

at the time of Acquisation of asset some Expenses are incurred i need to post this Expes to auc asset

how to do this one

please advise on this

Regards

sure

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Post the expenses to an internal order used for the purpose of AuC creation. Once the whole process is complete for the AuC, settle the internal order to the AuC and finally distribute the AuC to the required assets (AIUB/AIAB).