SAP-HR PROJECT DURATION TIME ESTIMATION

Former Member
0 Kudos

Hi Friends,

We are at the beginning of a project start-up.

I need to estimate the go-live time required for specific HR submodules in order to determine a feasible project scope.

My client has 250 employees.

The submodules we are considering include:

  • Personnel Administration

  • Organizational Management

  • Payroll (for Turkey)

  • Personnel Development

  • Appraisal System

  • Time Management (negative - no time evaluation needed)

  • Recruitment

  • Training & Event Management

According to your past experience, how much time would you propose for these submodules considering one consultant and one key user will be working full time on it?

Regards,

Dilek

Accepted Solutions (1)

Accepted Solutions (1)

sikindar_a
Active Contributor
0 Kudos

Personnel Administration

Organizational Management

Payroll (for Turkey)

Personnel Development

Appraisal System

Time Management (negative - no time evaluation needed)

Recruitment

Training & Event Management

hai

do u have any variations in the project i mean there are any roll out projects in this if not no issues

wht abt the status of to be documents i think ur in the BBP stage right did all the documents signed of from the process owner

more importantly the As IS documents which are given by the core users are ready with u

if there is no probelm in project evaluation and business blue print stage u can go off with in 6-9 months

Former Member
0 Kudos

Thanx Sikindar for the response!

No variations.

We are at the beginning of BBP stage ; BBP doc in preparation now.

As-is docs are ready.

By the way, can anyone provide me a module-by-module time estimation??

  • Personnel Administration

  • Organizational Management

  • Payroll (for Turkey)

  • Personnel Development

  • Appraisal System

  • Time Management (negative - no time evaluation needed)

  • Recruitment

  • Training & Event Management

Regards,

Dilek

Edited by: Dilek Ersoz on Oct 10, 2008 7:34 AM

sikindar_a
Active Contributor
0 Kudos

if there are no variations good

personnel administration - infotypes maintainece and all those things will be there so no probs can be delivered with in - 15 days to 20 days

organisational structure - use LSMW for bluck org structure so shd take only 5 to 10 days

pay roll - is there any scenarios u have to work on schemas and pcrs ( how many ESG EG PA PSA are there)

here i would say the testing part will take long time than the implimentation part so for implementiaion part 5 to 10 days

time management since the time status is 0 u can do in 5 to 10 days

rest PD , Rec , T&D, Apprisals i have not worked so it may take 20 to 30

concentrate on PY and PA and TM those will take more time if ther is any variations rest i dont have idea

Former Member
0 Kudos

Thanx Sikindar,

This was what I am seeking for!

Dilek

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi... 6 to 8 months should be decent...

Former Member
0 Kudos

Dear Dilek,

We have implemented all the said modules except Recruitment, but with Positive Time management & also number of employees are more. It took 6 months for us to project Sign Off.

Project implementation time frame is based on so many criteria like Scope, Quantity of records, Documentation, Custom development, Training, customer rapo, etc...

If everything finish within the deadline, you can implement within 6 months of time.

Good Luck.

Om.

Former Member
0 Kudos

thanx OM!

Anybody with a different estimation?

Dilek

Former Member
0 Kudos

Yep, no estimation.

Based on info given it's absolutely not possible to give an estimation.

How many CLA's do you have, do you have people with guaranteed net salaries, how many company specific regulations are in place etc. etc. etc.

Number of employees doesn't matter.

A implementation for 5000 employees can be easier than an implementation for 250 employees depending on the diversity in regulations within the population.

Wilfred.

Former Member
0 Kudos

Dear Dilek,

You are Welcome.

Good Luck

Om.

Former Member
0 Kudos

Hi Wilfred,

I know there are many other criteria that would affect the project duration time.

What I need, however, is a tough estimate, if possible.

Regarding my client, there are not many company specific regulations in place.

Regards,

Dilek

former_member583520
Active Contributor
0 Kudos

Hi Dilek,

Is it the project is in Project preparation stage.

Pls let me know on this.

Apart Training and Event mgt i woked remaining all the modules in one project.

I am only the SAP-HR consultant. If the project is in Project preparation stage it takes 6 months.

Thanks and Regards,

Revathi.

Former Member
0 Kudos

Hi Revathi,

Thanks for the response.

Project kick-off meeting has already been held.

However we have not yet made the scope determined.

What's 6 months? TEM?

Regards,

Dilek

former_member583520
Active Contributor
0 Kudos

Hi,

So, you are in Blue print stage right?

Thanks and Regards,

Revathi.

Former Member
0 Kudos

yes

Dilek

former_member583520
Active Contributor
0 Kudos

Hi,

It takes 6 months time to complete all the modules.

For this end user support is most important for this time.

Other wise it takes some more months.

Thanks and Regards,

Revathi.

Former Member
0 Kudos

Thanks for the estimation Revathi!

Any more ideas??

Dilek

former_member583520
Active Contributor
0 Kudos

Hi,

For z-reports purpose you can prepare simple specifications other wise it takes more time.

I think you are the one person working on this project right?

All the Best.

Thanks and Regards,

Revathi.