on 10-09-2008 7:53 AM
Hello,
How do we confirm a internal order?
what is the TC?
regards,
Ranjit
Hi
Do you mean to say, TECO. there is nothing called confirmation in intenal order. You can put...technically complete to an order.
regards
dinabandhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sap system monitorinternal order through entire system from initial cration through planing and posting all actual costs to the finalcial statemrents .
plsning kp46
budget ko22
crate ko01
and basic steps define order types and budget avalibility control
i.e define tolleranecelimits for avalibility control
sumathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What do you mean with confirm?
If you want to change the status, then use transaction KO02. But you cannot confirm like a production order, because there is no production.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.