on 10-09-2008 7:46 AM
Dear All,
I am using Maint Plan for generating regular service entry sheets. For these, I have created one Maint. Order(for settlement), one framework Order(MM). When call objects(entry sheets) are generating then after accepting those will update costs in Maint. Order.
Now, I settle Maint Order.(Order get TECO-ed now)
Then, next month next call object(SES) is not generating, But if at all I again reverse TECO and generate SES.............and continue process....
To avoid these, I have not TECO-ed and in REL state only i have settled the order.
1) Is this right process ???
2) OR is this OK to reverse TECO everytime after settlement..?
Or any better process for the above ?
regards
raj
Edited by: raj anand on Oct 9, 2008 9:00 AM
Raj,
With this process the maintenance order is acting as a "standing or bucket order".
- The order is left in the REL status for a particular duration (say one year)
- You can settle this order periodically (say monthly)
- Once your period is complete, you can TECO/CLSD the order. But you MUST update the maintenance plan with a new order which is REL otherwise the process will fail
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Raj,
The process which you have written is correct but reversing TECO to get service entry sheet is not at all correct.
Now just check you maintenace plan scheduling setting. Take scheduling paramenter 1 Yr. Then schedule your plan by IP10 and then see the list of plan generated and you will see the service entery sheet for all the planned if they called or save to call.
Regards,
Kaushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanx Kaushal & Thyarajan,
My sch. period is 365 days only and I am getting the full sch. days/planned dates. Out of which for first i have released Service entry sheet(SES) and on further processing TECO-ed order etc...etc.. But while clicking on next call object (manual release..before date), it tells me that Maint Order status is not suitable, so when I reverse TECO, it allows me.
Next alternative trial what I did that I didn't TECO and settled the Order. And then again Manually release the next call object(SES), it allows me..
Thats why I am asking what could be the correct process SAP proposes.??
Regards,
raj
Edited by: raj anand on Oct 10, 2008 7:32 AM
Thanks Thyagarajan,
Its understood that we should not TECO the Maint Order periodically,it can be done at the end of the Validity period. But don't you think that suppose validity period is two years then for each months SES generation and all costs will be gathered by Maint Order for the period of two years and cost is not going to the right allocation(say cost center) for long two years.
Points awarded to you. But practical stand point solution is required.
Raj
hi
i dont think to reverse the TECO ,if you are planned for monthly base and you are running the IP10 then it should generate the SES regularly .kindly check the above and revert back
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.