Hi,

while transfering data's from legacy to SAP only basic data and plant data views were tranfered with relevent values .

the remaining views has to be maintained in SAP. while going for additional views will the system allow us to create additional views after creation of material with only two views.

Is there any option to add views to the created material.pls provide.

Regards

suresh kanna

replied

It is possible to add views after creation of materials also.

but you can't add view's in th change mode, in material master create mode (MM01) select views what ever required for the same material number.