Hi PP Gurus,

I am trying to setup a configurable material which also contains a configurable component. For the configurable component ive already set a dependency which copies the characteristic value from the mother material. And since the component is in-house produced it has to create a planned order for the material.

My question is, how do i setup the configurable component so that the PLANNED ORDER/PRODUCTION ORDER created for the configurable component will contain the characteristics that were copied from the mother material?

I would very much appreciate if someone can help me..

Thank you,

Heinrick Palad

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Henrick,

for the Mother level material write a constraint such that it will pick up the required configuration of mother material.

for Example:

X IS_A (300) Mother material,

Y IS_A (300) Child material,

RESTRICTIONS:

You can define the restictions depending on your selection