PM MP-MPP querry

Former Member
0 Kudos

Hi all,

i am configuring centrlized mainte where our MP is100,MPP is 101,

now while assigning order types to MP config -- inside i can find a coloumn PIPI which is the MPP -- could any tell up to which i should assign my order types to MP or MPP.I would like to know all order settings are for MP or no ?

regards

pushpa

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

pushpa:

From OIOD you assign the Order Type to Maintenance Plant, moreover don't forget to set scheduling parameters and completion confirmation parameters

Hefni

Former Member
0 Kudos

hi hefni,

in continuation to the querry ...

1.The setting referes to Maintenance plant but inside the config it is mentioned PIPI -Which is planning plant...

2.Maintenance planner groups are to be assigned to MP or MPP ?

3.Task list planner groups are to be assigned to MP or MPP ?

regards

pushpa

Former Member
0 Kudos

hi all,

any replies ..?

regards

pushpa

former_member187991
Active Contributor
0 Kudos

hi

the order type are assigned to the MPP only ,it will be directly apply to the MP since you are assigning the MP to MPP

Maintenance planner group will be created for MPP whereas task list will be created for MP only

regards

thyagarajan

Former Member
0 Kudos

Hi,

For Plant Maintenance order types consern, you have to assign orders in to Planning plant wise only not plant .

Regards

charles edwin