Hello friends,
I have been doing a SP's Upgrade in my SNDBOX and I have come across a few issues.
1.Even though everything under With Modification Assistant is green (programs, function groups, multiple use includes) the With Modification Assistant is Blue in color. What might be the reason?
2.I fixed all the modifications and when I ran SPAM i came with and error as shown:
Internal error: SPAM_CONFIRM_PATCH -> WRONG_STATUS: R
Does any one have an idea as to why the error has occurred and how to fix it?
thank you
Druva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
after you do the modifications to the repository objects
click the tab GOTO and follow the path
GOTO --> STATUS --> QUEUE --> Confirm Queue
This should get you out of the following error.
internal error: SPAM_CONFIRM_PATCH -> WRONG_STATUS: R
now run the import again and at the end click confirm queue under the tab Support Package.
Thank you Juan for the link.
I could figure out the problem and have it in a more clear picture
Edited by: Druva Simha Kolli on Oct 8, 2008 10:43 PM
I answered it myself with help from juan
Edited by: Druva Simha Kolli on Oct 8, 2008 10:45 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.