on 10-08-2008 7:32 PM
Hi all
I have a requirement. I have a sales order for a product for requirement may be after 1 yr. The system should not raise any procurement proposal for that as the requirement date is too long. It should only create proposals which fall within a range of 6 months from the current date.
My MRP type is normal PD . Where do I have to set this? If I give the planning horizon as around 150 days also, this requirement is captured and creating a planned order.
Points are assured for the appropriate answer.
Thank you in advance
Chandra
Hi Chandra,
Make sure you are using processing key NETPL (Net Change in Planning Horizon) and the planning horizon is maintained correctly for plant / MRP group in OMDX.
Cheers,
Himanshu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Himashu
I am running my MRP with the parameter NETCH every day and once in every week it will be run in the regenerative mode. Even when I run in the regenerative mode, the Sales Order which is due for after 1 yr should not create a procurement proposal. If the requirement falls within 6 months from today, it should create a proposal. Is this possible?
Thank you
Chandra
Hi,
Instead of running parameter NETCH, you can use NETPL daily basis. So system will consider upto planning horizon.
You can avoid running Regenerative planning as weekly basis. This is required at the time of 1st MRP run after implementation. Not possible to reduce the planning horizon in regenerative planning.
Regards,
Dharma