Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Completion of Preventive Maintenance

Hi guys,

I was in a assumption that if we had given shif factor as 100% and didn`t flag the completion requirement...the schedule adjust based upon the completion of the work order.

ex : 01.01.2008 is the start date and it has a monthly frequency which goes on 02.01.2008 and so on.

lets assume if the work completed on 01.15.2008 ....so automatically next schedule will move on to 02.15.2008 ? as we had given the shif factor as 100% ..if yes how the system calculate the completing date...based on TECO or Based on time confirmation ? I know if we keep shift factor as blank and unflag the completion rqmt...schedule would not get affected.

and also how the system calculate the basic start date and basic finish date without using the priority?

pls advice

Vijay

Not what you were looking for? View more on this topic or Ask a question