on 10-08-2008 6:09 PM
Dear all,
With respect to the above subject, we are trying to calculate the costing
for the semifinsihed material using a T-code CK11N.
But, Most of the operations carried out by the job workers are on our
machinery. So, whenever we are creating a routing for operation in our
factory we are mentioning the work center and the control key as PP02. But,
when we are trying to capture operation cost for the PP02 it is taking
only the cost which is mentioned in the purchase info records or which is
mentioned in routing.
So, please specify what necessary change in the fields are required so that we can capture the
exact cost of the components.
Best regards,
Shailesh
.
How about creating Activity Types for each machine and assiging these activities to the material BOM? The cost centre(s) assigned to the corresponding work centres will help calculate the unit cost for the sake of product costing.
Cheers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.