CJ20N Project Activity Level Actual Dates Auto-Populating

Former Member
0 Kudos

Greetings All,

I have a question with regards to t-code CJ20N. Looking at the Activity level of a project, under the dates tab is a field for actual start (AFVGD-ISDD) and actual finish dates (AFVGD-IEDD). They are auto populating and we are not sure why. We do not want these fields to be auto populated. They are messing up resource allocation via CMP3 for us.

I have been looking around and have not been able to find any information on this. Any help is appreitated.

Thanks all!

Accepted Solutions (1)

Accepted Solutions (1)

former_member214674
Contributor
0 Kudos

Hi,

Whenever you confirm activity...it will result post actual dates..

Regards

Abhinay

Former Member
0 Kudos

Is there any way to stop this from happening? Like some sort of configuration. Also, is this the only way that those will get populated?

former_member214674
Contributor
0 Kudos

Hi,

Goto tcode OPST...and there is a check box propose date....

I think if you can uncheck this....w'ld solve ur problem.

Regards

Abhinay