Blocked Stock in Process Order

Hello, Expert,

When i doing the process order confirmation, total 100 pc for material A, is it possible to post 95 pc into quality inspection (stock type control for GR in process order header) and the other 5 pc posted to Blocked stock? In our real practise, these 5 pcs are damaged products.

If it's possible, which movement type shall i use and how it works?

Secondly, in the process order, can i consume the components in blocked type? (not Unrestricted Use)

Many thanks,

Vincent

Former Member
Former Member replied

Hi,

Activate inspection type 04 in QM view of material master .

Do the GR against production order inspection lot is crated.

Do the UD for this inspction lot and post to blocked or un stock .

Regards

Sandeep