hello

I would like to ask about plannig in CO:

I would like to plan cost elements on CCtr but I would like to divide possibility to plan between 2 users:

CCtr 1000

user 1 can plan on cost elements:

4100,

4200,

user 2 can plan on cost elements

4400,

7800,

user 1 mustn't plan on cost elements 4400 and 7800 and user 2 mustn't plan on 4100, 4200.

Is such situation available on one CCtr? I think it isn't but not sure about it.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

This is more of a user trainning issue.

train your user1 to not plan on 4400 and 7800 cost element and train user2 to not plan on 4100 and 4200.

one more option would be check with your security consultant,is there any authorization object on cost element.which solve your problem.

Thanks,

Rau

adam_sobkowicz2
Active Participant
0 Kudos

for me this is not a trainnig issue, this is a security

Is there any authentication object for cost elements ? This was my question?

Former Member
0 Kudos

Try using object K_CSKB_PLA field value KSTAR

Regards

Sreenivas

Answers (0)