on 10-08-2008 2:06 PM
Hi,
Please enlight me...what actually the function of SKF.
I create a project structure all using WBS (include WBS for activity)
I create master data SKF with type 2 (total value) and unit of measurement is hectare (HA).
I am going to use this SKF to allocate how many hectare done for an activity (using WBS)
I run tcode KB31n ...choose scr variant WBS/order .I put SKF quantity and WBS element.
My question are :
1st. Can i use this SKF to allocate how many hectare for an activity done
2nd. Is there any standard report to check the actual value for it?
Plz advice.
Cheers,
Nies
yes you can use SKF
report S_ALR_87013548
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Is it possible to make a validation between WBS and SKF?
Let say i have a project with structure :
Proj Def : ABCD
WBS level 1 : ABCD1
WBS level 2 : ABCD2
I have two SKF : 1st. SKF1 and SKF2
I need only SKF1 can be used for project ABCD (Wbs level1 and 2) ...user cannot use SKF2 with project ABCD...
Any clue?
Plz advice.
Cheers,
Nies
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.