Hi Experts,
I am facing a problem of optimizer not respecting the fixed lot size defined in product master. Explanation is as follows
Product 'A' must be produced in a fixed lot of 5 tons. I have maintained the same in Lot size tab of product master. I am using discrete optimizer with Minimum PPM/PDS Lot Size & Integral Lot Size both enabled in the optimizer profile. I have also enabled the discretization in the PPM.
Now if the demand is 17 tons, the expected output is to have 4 orders of 5 tons each. However system is creating 3 orders of 5 tons & the last order of 2 tons to cover the demand of 17 tons. I have maintained storage cost for the product. If I don't maintain this, then the system plans much more quantities than the requirement.
Can anyone help to solve the issue ?
Thanks in advance
Regards
Sandeep
Hi
Please check if your last lot is falling in the bucket that is outside the discretization horizon maintained in Opt profile.
I will come back if I get something more.
Take care.
Nitin Thatte
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.