Operation splitt

Former Member
0 Kudos

Hi PP Experts,

Can anybody please explain me what is operation splitting,when it require and how to do it.

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Splitting is to reduce the lead time of the Operation.

Through splitting, an operation is split into several sub-operations that can be processed in parallel with each other. this reduces the operation lead time.

You need to maintain the "Required splitting" in the operation details screnn of routing CA02. Number of splits and Minimum processing time is required.

The number of splits specifies the maximum number of splits that may take place for the Operation. if the Minimum processing time is not maintained splitting will not take place.

An operation is split if it is carried out on several machines or by several persons at the same time.

If we do the splitting.

The processing time/execution time becomes shorter.

Setup and teardown must be carried out more than once for the operation.

Please refer this link also,

[Splitting|http://help.sap.com/saphelp_46c/helpdata/en/7e/d419b7455911d189400000e8323c4f/frameset.htm]

Hope this helps..

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

Splitting

If an operation is usually carried out on several machines or by several employees at the same time, the operation can be split. Splitting is defined in the operation.

Splitting an operation has the following effects:

The processing time/execution time is reduced compared with an operation that is not split

Multiple setup and teardown is required for the operation

The system selects the minimum from one of the following as the actual number of splits :

Number of splits in the operation

Number of individual capacities of the work center capacity that is relevant to scheduling

Splitting can be done by following procedure:

Go to CO02--> Operation Overview--> Select Operation -> Go to Operation Details->Select Splitting Tab

Under Splitting Tab

tick check box of Required Splitting

Maintain required values for Maximum No of Splits, Actual No of Splits,Minimum Processing time and save the settings.

HOpe this helps.

Award points if useful.