on 10-08-2008 12:36 PM
Hi,
Can you explain me the signification of each line (in yellow) that we find in the report gived by Tcode : S_ALR_87012176
there are 5 lines :
Net ?
Dsc ?
Pmt ?
Old ?
Ovd ?
Please Help
Regards.
Edited by: jehade el aoumari on Oct 8, 2008 1:08 PM
Answer is imaginary
Net = Net Value
Dsc = Discount
Pmt = Payment
Old = ?? not able to guess
Ovd = Alternate amount
Any one else?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The explanation are as follows:
1) Aging schedule for open items by due date for net payment
Displayed next to "Net"
Calculation: Due date for net payment - key date
2) Due date forecast using the first cash discount days
Displayed next to "Dsc"
Calculation: Baseline date for payment + cash discount days 1 - key date
3) Probability of payment based on the weighted incoming payments in the past
Displayed next to "Pmt"
Calculation: Baseline date for pmnt + cash disc.days 1 + average days in arrears
4) Days overdue of items that are due
Displayed next to "Ovd"
Calculation: Key date - due date for net payment
The analysis types "Net", "Dsc", "Pay" are a future time frame for forecasting incoming payments. "Ovd" is the time frame for the past for analyzing overdue items.
Not sure about the "old" analysis.
Regards,
Ramanand
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.