Hi PP Experts,Can anybody explain me pegged requirement means what with example.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Pegged requirements means material which is dependent to their higher level material.

Use tcode MD09 to see pegged requirement.

Example. A material having planned order of 100 qty. If you check with pegged requirement, the result will be how many quantities dependent to higher level material in qty of 100.

Regards,

Dharma

Former Member
0 Kudos

Hi,

The next higher level of the bill of material that is the source of the requirement in a lower level, in the evaluations for material requirements planning.

If it is an MTO system then you will have the pegging right upto the sales order.

from any MRP element (planned order /Pur reqsn) you can trace it upto the sales order.

In an MTS system you can trace upto the planned order / production order of the Finished good.

Regards,

Ashok

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Peggeed requirement is nothing but it represents the Higer level material. For example if raw material purchase requisition for 100 nos, then it is a Pegged Requiremet of the Assembly or the FERT. Simple its a dependent requiremnt for FERT or SFG.

MD09 is used to find out the Pegged Requirement. If you give the Purchase Requisitiion of the Raw material, then system will tell you the pegged requirement i.e. the production order order to which the purchase requisition belongs to.

Pegged requirement may be a Sales Order,Reservation,Production Order,Project,Network,WBS etc.

Select one MRP element in MD04 screen and if you select pegged requirements system will show you these elements created for any higher level material or not.

Please refer for more help.

http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d302f44af11d182b40000e829fbfe/frameset.htm