on 10-08-2008 11:30 AM
Hello,
Trying to integrate an EDI message (DELINS) I am getting a number 51 error: "Scheduling agreements were found with differing sales units".
If I check the EDI message the sales units are PCE (ARD line) and in our Schedule agreement (VA33), the sales units are EA.
So easily, it seems that the error is here but, when I try to modify the sales units in the Idoc (WE19) and change PCE for EA in segment E1EDP10 I get a dump.
So any ideas? Somehow it should be possible to avoid this kind of errors asking the system not to check sales units or something like this?
The option of changing the units in the Material Master and then in the Schedule agreement is not my favourite.
Thank you
Internal error
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello again,
I've tried changing the unit in the material master, but then after doing all the necessary changes I get a new dump error.
It seems like some kind of incompatibility between the SAP measure unit (EA) and the Idoc measure unit (PCE).
I've also tried changing in the customizing the unit of measures changing the EA ISO code to PCE instead of EA, but then again I get the dump when trying to integrate.
Ideas?
Thank you
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.