Former Member
0 Kudos

Hi friends,

What is the t code for display committment line items for project.

Reg

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

ansd

Former Member
0 Kudos

Hi,

You can se it's thru' S_ALR_87013558 & in detail cji5.

Regards,

Vishal Kr. Sharma

Former Member
0 Kudos

Hi,

How can we get following column in output screen .

Regards

1. Debit date

2.Object(WBS element)

3.Cost element

4.Total quantity

5.Unit of measure

6.Value in object currency

7.Reference document no.

virendra_pal
Active Contributor
0 Kudos

in CJI5 go to display variant and select fields

save variant for future if required

Former Member
0 Kudos

Hi,

You can get it's thru' CJI5.

Pls. open the Layout add the relevent field after execute report.

Regards,

Vishal Kr. Sharma

Former Member
0 Kudos

Dear Amit ,

you can see commitment by standerd budget report

S_ALR_87013558 Budget/Actual/Commitment/Rem

or u can also see by cjI5

Regards

Vivek