Hi All,

I have a DMR (for Inwards -01type) of 4 Stages. 3 are of Skip status. Fourth one is Inspection stage.

I have made the following rules for Stage Change,

For 1st Stage - Inital Stage and Skip

OK--

No of Skips------1

New Stage-------2

NOT OK---

Rej No------1

New Stage---4

In the same way, i have made the rules for other stage changes. What happens is, Lot is got generated @ GR, with 1st Stage..i.e) SKIP.

If I reject the lot by giving REJECTED at UD, by rule it should move to Fourth Inspection stage.

But it actually moves to second stage for the next Lot. Same thing happens with all the other stages.

My doubt is Stage change occurs w.r.t NO OF SKIPS and not on the UD given.

Note: I have selected DMR - for Usage Decision

In QP01 - DMR at Lot level

DMR and Sampling procedure rule assigned in QDB1

All MICs' are Optional Characteristics

Please guide me.

Thnx in advance

Sam

Former Member
Former Member replied

Hi

Why are creating it like this. You can achieve the same in 2 steps only.

e.g.

Step 1 -- 3 skips for ok -- move to step 2 for rejection &

Step 2 -- 1 inspection for ok -- next step 2 for rejection

See if it works