on 10-08-2008 9:23 AM
Hi All PP Gurus,
Can anybody tell me the answer of following
How we can correct the process order confirmation data posted in the previous month.
Dear,
I hope this link is helpful
http://help.sap.com/saphelp_40b/helpdata/ru/fc/6cec6eb435d1118b3f0060b03ca329/content.htm
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
for alredy confirmed data - cancel the confirmationfor the perticular order.
and redo the confirmation with correcting the data.
1.if Inspection lot is created for previous confirmation, the lot will not get canceleld(if UD is done)
2.If tehre is no stock of the order, then you get the COGI errors.
-ashok
Edited by: ASHOK on Oct 8, 2008 2:01 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ashok/Brahmankar,
Actually i am facing the following problem:-
1) If you cancel the confirmation done in the previous month by the tcode CORS, the CO document is posted in the previous period because we cannot change the posting date in CORS. But the previous period is already closed.
Can we change the posting date in CORS manually? Or do you have any other idea?
2) When reading the master data in COR2, I face the error because the status of PO is already set as 'DLV'.
Do we need to read the master data even when the value is changed in KP26?
Thanks,
Narayan
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.