ps assembly processing:WBS have not be created when saving the sales order

In the ps assembly processing, I want to generate a network when I create a sales order. So I did the following steps:

1-Use the TCODE cj91 to create a standard WBS "E-000007.1".

2-Use the TCODE cn01 to create a standard network "10000000" and assign the standard WBS "E-000007.1" to it.

3-Use the TCODE cn08 to config the Network Parameters from Sales Order like below:

Material number : 600000-000000-0009

Order Type : Z301

Std network : 10000000

Class Type : 020

Network Profile : Z0001

MRP Controller : 001

Std WBS element : E-000007.1

4-Use the TCODE va01 to create a sales order and add an item with the material "600000-000000-0009" and save.

When the SAP R/3 System is saving the sales order, a WBS ought to be created u2013 based on the assignment of the standard network to the standard project.But I could not found the WBS.I thought I have do all of steps and could not found the reason.

So I need the experts give me some useful advice and reference to resolve the problem.Thank you.

Regards

Yoda

replied

hi ,

Pls try to get Strategy Group "85" or "83" in the Material Master of the Material u r using in Va01,

Recreate the Sales Order after changing the Strategy group , hope this will solve ur prob

regards

Hemant

0 View this answer in context

Helpful Answer