please help in config of bills of material scinario and it is as bellow..

Former Member
0 Kudos

Dear all

my requirement is to create a multi level bom.

i can explain by an example

i am having a FERTmaterial name as FERT-A

under that 3more FERT materias are there Called

FERT1.

FERT2

FERT3

and 3 semifinishhed product which ll be assembled in the site only

called as

HALB1

HALB2

HALB3

and we also has some loose tools which alo been assembled at site

Spare 1

spare 2

spare 3

now we are despatching each group separately

like FERTs ,HALBS and Loose tools and we are billing them as per the despatches

now we need that when we prepare a bom it should show all the bom items in the sales order and the parts which are despatched they should be come as inactive or where the parial delivery of some of the bom item has happened should come with the message or some information that the partial delivery has happend.

so how to configure all this in SAP.

Edited by: subu sd on Oct 10, 2008 7:52 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

no answer