Hi Sap Gurus,
Can ve delimit object ( S & O ) validity period . I know we can delimit objects relationship . I try to delimit obejct but the system show masage " Infotype 1000 can only be delimited via dilimited object"
Regards
Yogesh Kumar
change the time constraint of IT1000 from 1 to 3. it shud work
cheers
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
go to transaction PP01 and select object type and object ID of object to be delimited.
Subsequentuly in the menu-bar go to 'Object' --> 'Delimit'.
This will do the trick.
Wilfred.
PS This action will delimit all recorded data, so not only IT1000 but automatically also all other infotypes recorded for this object.
Hi,
If u select Change for Org units Object infotype and change the end date from 31.12.9999, & Save,it accepts..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi sir,
Thanks for you reply , As per your suggestion we can not change the end date of objects( infotyep 1000 ) . I try thru po13 or po10 but the valadity period is in gray shade you cant change dates . You have only option to change description there. There is only one way i found thru PPOM_old and ppome with the enhancement object distribution . And thru ppom_old we delimit the objects validity period . Please revert if u have other suggestion also.
Yogesh rahar
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.