Capacity Availability Check

Former Member
0 Kudos

For the production order after capacity availability check, system is showing the capacity is available, even the order execution in the same period and on the same work center.

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please check the overload on work center in CM01 or In CM25 are you getting any overlaod at WC.

Did you release the production order?

what is setting you have in SPRO for availabilityy cheking for the capacity and which over all profile you have assigned to the order type?

Regards,

R.Brahmankar