There are any way to customize fixed weekday for GR.

Former Member
0 Kudos

Hi All,

Please let me know there are any ways to customize or any other setting to set the fixed weekday (Monday to Friday) for good receipts by vendor and plant.

Example: Material A, delivery leadtime 10 days, fixed good receipt weekday is "Thursday" for vendor V and plant XYZ.

It means that:

A purchase order created on 30 September for material u2018Au2019 , plant XYZ and vendor V having a goods receipt date of Friday 10 October.

As the fixed receipt date is Thursday, the actual delivery should occur on Thursday '14 October'.

This receipt date is based on fixed weekday. It must be the one computed by MRP calculation and appears on MD04 stock requirement list as actual receipt date.

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

former_member581212
Active Contributor
0 Kudos

hi,

For MRP, the Planning calender is always defined from MD25, to change it use MD26, and display it from MD27...

I think you can schedule it here.....