Cost component split costed with value of zero

Hello Friends,

I am in big trubble due to this error messge

"Cost component split costed with value of zero"

and with this message a lot of causes are given. some are as follows about which i need your help.

-the quantity structure is not relevant to costing

the part of the cost component split that is relevant to inventory valuation is zero

When i create process order then itemizatoin/cost component view/analysis can be done, also i have run adhoc cost estimate thru ck11n.

But when i run std.cost estimate , then only i am facing this problem.

Please help me as soon as possible. i am in big tuble now.

Thanks

Ravi