Hi Experts,

Can I use MF50 planning table for discrtet manufacturing.

See I have an scheduling agreement from customer. But I want to plan my production qty. according to my tool availabilty.

So I was deciding to plan my prod. qty in MF50. So please guide me if I can use that for discrete manufacturing? Because after planning in MF50 I will run the MRP and then will convert the plnd. order into prod. order. So If I will put the planning of Finish material then after running MRP requirement will go to the down level of HALB in which one of my HALB depends on tool avaialbilty.

Please guide and help.

Regards

Deepak Sharma

Former Member
Former Member replied

Hi,

You can use very much planning table MF50 for Discreate manufacturing. This procedure is already in use.

Regards,

Dharma