Bom Selection

Former Member
0 Kudos

Hi Friends

I am working on a Long Term Planning Scenario, while simulating the client will use various BOMs to check the costing during Annual Planning run and also for Planning run for a Quarter, how can I select the BOM as required during LTP-MRP Run? Also plz let me how to configure the BOM selection ID??

Jade

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

BOM selection will be done by automatically, manually not possible. In material master MRP4 view BOM selection option given by,

1. Lot size

2. Date

3. By production version

4. Only by prod version.

System will select according to that only.

Before configuring BOM selection ID, we have to configure Order of priority b ytcode OS31. In this create selection ID no by priority wise respect to BOM usage.

Use this BOM selection ID in BOM application as required.

Regards,

Dharma