Budget Allocation dan Actual per month

Former Member
0 Kudos

Hi All,

Can we monitor budget in PS by monthly not yearly? Can we monitor the actual in PS by monthly ?

I am going to create custom report for it. anyone could advice the table that can be used?

Plz advice.

Cheers,

Nies

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi,

see report s_alr_87100185 - Actual costs for each month and s_alr_87100186 - planned costs for each month..

maybe you could maintain your budget as your planned cost (CJR2) at the same time so it would appear in monthly reporting..

regards

Former Member
0 Kudos

Hi,

What the table store the report s_alr_87100185 - Actual costs for each month and the table for s_alr_87100186 - planned costs for each month..

Plz help, i need to create custom report for my Fspecification.

Cheers,

Nies

virendra_pal
Active Contributor
0 Kudos

table RPSCO is best for plan and actual values

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

you can see it in standerd report in S_ALR_87013558 - Costs -> Budget-Related -> Budget/Actual/Commitment/Rem by selecting grafical layout.

Regards,

vivek Tripathi

Former Member
0 Kudos

Hi,

Yes you can monitor it's on monthly basis.

Open the slr report S_ALR_87013558 and click on Graphical report output.

Then execute.

Select the WBS Actual amount & click on Under navigation Period/Year .

Now you can get Monthwise actual.

Regards,

Vishal Kr. Sharma