CL Quota not updating in IT2006 after time evaluation

Former Member
0 Kudos

Dear All,

Employees who are in probation period, 0.5 day per month casual leave should be created through time evaluation.

but its not happening for some employees, so i run time evaluation manually T-Code PT60 (actual run). and checked the log. In the log tree its appearing time type 9DCL = 0.50 . even though its not updating in infotype 2006.

what would be the problem. what all i have to check more.

kind regards.

Dinesh.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

go to table V_T559L and go to Base entitlement and do the following :

1. put 0.5 in constant field.

2. click Accrual period radio button

3. save the base entitlement and go to selection rule and click the accrual tab.

4. in the accrual tab click the Month radio button.

5. now execute time evaluation.

it should work, if all other customizations are correct.

regards

Pradeep

Answers (2)

Answers (2)

shreyasi_salvi2
Contributor
0 Kudos

Hi,

You will need to check whether the CL time type is attached to the absence quota type in Accrual entitlement under Generation Rules for Quota type selection.

Regards,

Shreyasi.

sikindar_a
Active Contributor
0 Kudos

did u check the counting rule in T556C and also check the valuation rule in T554C