on 10-07-2008 5:31 PM
The parents material lot size is fixed lot size , child component lot size is 2 week lot size. ( ie. 2 week = 10 Days ).
question:
If the demand for parent material in month,after MRP run the dependent requirement for child component also getting generate only one planned order.
What are the possibilities if the parent demand in month, child requirement is needed in weekly basis .Any chance to get the child requirement in weekly by changing lot size or any other possibilities.
Hi
You can maintain for dependent material as biweekly lot size.
week days depends on your factory calender assignd=ed to the respective plant.
Try having like this.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your answer. if we change the lot size for dependent material to weekly , biweekly or fixed etc....
The dependent req. will generate according to the lot size that is absolutely correct. but planned order or purchase req. will create according to the parent demand (ie .Adding of dependant req. what ever falling with in the lot size period and for that quantity planned order or purchase req. is getting created )
Actually my requirement is for the each dependent requirement one planned order should get generate .
Hi,
Create a planned order for a child material respect to parent material requirement date is not a easy with this situation.
But you can split the child material planned order to as required by using lot size FS - Fixing & splitting. assign this lot size to child material. System will ask for fixed qty, rounding value and enter the takt time.
System will split the planned order with rounding value. Planned order will go behind as you mentioned days in Takt time.
Regards,
Dharma