workcenter with no of capacity 10

Hi

I have one work center with no of capacity 10

i have cycle time for one operation with say only no of capacity as 1 = 15 sec

do i have to change cycle time also when i am changing no of capacity from 1 to 10

I mean how the calculation would take place , available capacity OR Load

Is it must to use split with this ??

Please help in this regard

Regards

Amit

Former Member
Former Member replied

Hi,

Suppose the production order qty is 10 no. With No. of individual capacity=1, the cycle time is 15 sec for 1 no.So the total processing time is 150 sec (15*10). When the same operation is executed in 10 Capacities, the work is splitted equally to all the 10 capacitites and hence the total processing time will be 15 sec for producing 10no with 10 individual capacities. For this maintain the formula for scheduling as the SAP standard formula SAP002.

Now your available capacity is 10 with the operating time as per the shifts defined. If one capacity works for 8 hrs, then the available time for this work center will be 80 hrs (8*10) with 10 individual capaciities.

For this, maintain no. of individual capacity=10 in Work center capacity header. In routing, maintain No. of splits=10 with the Check box "Required splitting" checked.

Hope this helps for your requireemnt.

-Thaila Shree

0 View this answer in context