Bapi for Process Order Detail?

Former Member
0 Kudos

Hi, I'm trying to change line items on a process order. I have searched SAP for a BAPI with no luck. I found a BAPI to change the header record of a Process order but nothing to change the detail.

Please let me know if there is a way to accomplish this without using a BDC.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

BAPI_PROCORD_CHANGE - Change Process Order only allow me to change header data.

BAPI_PROCORD_GET_DETAIL.

I don't think there is any other standard BAPI avialable for your requirement.

Please refer this also,

http://help.sap.com/saphelp_nw04/helpdata/en/e0/9eb2370f9cbe68e10000009b38f8cf/frameset.htm

Regards,

R.Brahmankar

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks. I ended up writing a BDC.

Former Member
0 Kudos

When you say changing Process order Item details..are you referring to Process Order Component details?? or some other stuff....