Capcity availability check in production order

Hi

Details of my scenario are as follows:

Work center L1 - Available time per day is 21 hrs or 1260 mins (from work center 001 capacity tab).

1. Production order A-

Work center - L1

Set up time - 120 mins

Machine time - 1000 mins

2. Production order B-

Work center - L1

Set up time - 120 mins

Machine time - 1000 mins

As per the availability capcity of work center L1, system should propose capacity is not available at the time of clicking capacity check in production order B. But it is not so in either of this orders.

It shows in both orders, capacity available. But when i check in CM01, it shows work center is overloaded on that particular day.

Kindly let me know how to resolve this

Thanks in advance